Designing Project Stakeholder Management Plan at Coffee Plant Construction Project for Successful Initiating Phase in Ciwidey

  • Devi Pratami Department of Industrial Engineering, School of Industrial Engineering, Telkom University
  • Nurfitri Ayu Puspitasari Department of Industrial Engineering, School of Industrial Engineering, Telkom University
  • Imam Haryono Department of Industrial Engineering, School of Industrial Engineering, Telkom University

Abstract

CV Trianom Agrotektur is a company engaged in coffee industry. Due to high demand and expanded business process the company owner is going to build a new plant in Ciwidey. The current plant cannot cover the whole business process of in processing coffee beans. The extensification towards the plant requires some guidance to lead the successful contruction project. However, building plants in rural area is not a simple thing. There should be some investigation towards stakeholders’ needs/interests or requirements. The project should also face an issue pertaining to management, i.e. how to manage stakeholders who still keep their local tradition. This study is aimed at designing project stakeholder management plan based on PMBOK 5 edition. The study shows that there are 21 stakeholders classified in 4 quadrants. Those stakeholders will be managed based on their power and interest level.

Published
2017-07-31
How to Cite
PRATAMI, Devi; PUSPITASARI, Nurfitri Ayu; HARYONO, Imam. Designing Project Stakeholder Management Plan at Coffee Plant Construction Project for Successful Initiating Phase in Ciwidey. International Journal of Innovation in Enterprise System, [S.l.], v. 1, n. 01, p. 19-28, july 2017. ISSN 2580-3050. Available at: <http://ijies.sie.telkomuniversity.ac.id/index.php/IJIES/article/view/28>. Date accessed: 21 sep. 2017. doi: https://doi.org/10.25124/ijies.v1i01.28.
Section
Articles

Most read articles by the same author(s)

Obs.: This plugin requires at least one statistics/report plugin to be enabled. If your statistics plugins provide more than one metric then please also select a main metric on the admin's site settings page and/or on the journal manager's settings pages.