Schedule Acceleration Planning in Construction Project (Case Study: Japek II Selatan Tollroad)

  • Aziz Irsyad School of Industrial and System Engineering
  • Ika Arum Puspita Telkom University
  • Wawan Tripiawan Telkom University
Keywords: CPM, Planning, Overtime, Crashing, Scheduling

Abstract

This study focuses on the remaining work at stations (STA) 53+950 to 54+550 in Jakarta – Cikampek II Selatan Toll Road Package III project to find the critical path, completion durations, and project costs before and after acceleration. The CPM Technique was used to compile network planning diagrams, determine the critical path and project duration. Crashing Project was applied to crash schedule through the total project duration and cost whose changes due to the implementation of the crashing method. The critical path was found in mobilization, tree felling, clearing, dig and haul, borrow material, subgrade preparation, base course (A grade), subbase course (B grade), drainage layer, lean concrete (t=10 cm), concrete pavement, concrete barrier type B, and signage. In the CPM, the duration of project completion is 214 days. The total project budget under normal circumstances is Rp22.073.412.654. After accelerating with the Crashing Project by proposed overtime was obtained the reduced total cost of Rp32.004.882 from the total normal cost of Rp22.073.412.654 to Rp22.041.407.771 with an optimum duration of 183 days.

References

[1] M. Amry, S. Hardjomuljadi, and C. A. Makarim, “KEGAGALAN KONSTRUKSI DAN KEGAGALAN BANGUNAN DALAM PERSPEKTIF KEBERLANJUTAN KONSTRUKSI,” no. November, pp. 407–417, 2019.
[2] R. Maharesi, “Penjadwalan Proyek Dengan Menggabungkan Metode PERT Dan CPM Retno Maharesi,” pp. 51–60, 2002.
[3] W. I. Ervianto, Manajemen Proyek Konstruksi, Yogyakarta: Andi, 2002.
[4] M. Priyo and Sartika, “Analisis Waktu Pelaksanaan Proyek Konstruksi dengan Variasi Penambahan Jam Kerja,” vol. 17, no. 2, pp. 98–105, 2014.
[5] PMI, A guide to the project management body of knowledge (PMBOK® guide), 6th ed. Philadelphia: Project Management Institute Inc, 2017.
[6] T. H. Handoko, Manajemen Produksi dan Operasi, 1st ed. Yogyakarta: BPFE, 2010.
[7] J. K. Lumbanbatu and Syahrizal, “ANALISIS PERCEPATAN WAKTU PROYEK DENGAN TAMBAHAN BIAYA YANG OPTIMUM (Studi Kasus : Proyek Pembangunan Gedung Sekolah Yayasan Pelita Bangsa di Jl. Iskandar Muda Medan, Sumatera Utara),” 2017.
[8] Z. S. P. Anugerah, D. Pratami, and M. D. Akbar, “Designing project schedule using crashing method to compress the fiber to the home project schedule,” Int. J. Ind. Optim., vol. 2, no. 1, p. 51, 2021, doi: 10.12928/ijio.v2i1.3025.
[9] N. Khodijah, S. Yahdin, and N. Dewi, “Optimalisasi Pelaksanaan Proyek Pembangunan Persinyalan Elektrik di Stasiun Kertapati dengan Penerapan Metode Crash Program,” J. Penelit. Sains, vol. 16, no. 2, p. 168309, 2013.
[10] M. Priyo and A. Sumanto, “Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off : Studi Kasus Proyek Pembangunan Prasarana,” Semesta Tek., vol. 19, no. 1, pp. 1–15, 2016.
[11] N. D. Afifi, I. A. Puspita, and M. D. Akbar, “Developing Schedule With Linear Programming (Case Study: STTF II Project Komplek Sukamukti Banjaran),” Int. J. Innov. Enterp. Syst., vol. 4, no. 02, pp. 34–45, 2020, doi: 10.25124/ijies.v4i02.77.
[12] L. J. Krajewski, L. P. Ritzman, and M. K. Malhotra, Operation Management. New Jersey: Pearson, 2010.
[13] J. M. Nicholas and H. Steyn, “Project Management for Engineering, Business and Technology,” Proj. Manag. Eng. Bus. Technol., 2017, doi: 10.4324/9781315676319.
[14] Y. Stefanus, I. Wijatmiko, and E. A. Suryo, “Analisis Percepatan Waktu Penyelesaian Proyek Menggunakan Metode Fast-Track Dan Crash Program,” J. Media Tek. Sipil, vol. 15, no. 1, p. 76, 2017, doi: 10.22219/jmts.v15i1.4494.
[15] W. Hartono, M. N. P. Wati, and Sugiyarto, “Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Penambahan Jam Kerja Lembur Optimum (Studi Kasus Proyek Pembangunan Gedung Kantor Kelurahan Ketelan, Surakarta),” e-Jurnal Matriks Tek. Sipil, pp. 1000–1004, 2015, [Online]. Available: https://103.23.224.239/matriks/article/view/37042.
Published
2022-01-31
How to Cite
Irsyad, A., Puspita, I., & Tripiawan, W. (2022, January 31). Schedule Acceleration Planning in Construction Project (Case Study: Japek II Selatan Tollroad). International Journal of Innovation in Enterprise System, 6(01), 24-37. https://doi.org/https://doi.org/10.25124/ijies.v6i01.145